In Arizona, how long does a contractor have to submit a lien after a notice of completion?

Study for the Arizona Statutes and Rules Exam. Prepare with comprehensive questions and detailed explanations. Ace your exam with confidence!

In Arizona, when a notice of completion has been filed, a contractor has 60 days to submit a lien. This timeframe is important because it provides a clear deadline for contractors to enforce their rights for payment under the mechanics' lien law. The lien must be recorded within this period to ensure that the contractor's claim for payment is protected and can be enforced against the property in question.

Meeting this timeline is crucial to avoid losing potential rights to recover unpaid balances for work completed. It ensures that contractors act promptly after a notice of completion is issued, helping to facilitate an effective resolution of any payment disputes.